Moving plan for Phase I


People affected by the renovation will be moved into temporary spaces while the construction takes place. Relocated space will be located in The Sunrise Building, Fireside Lounge, Performance Lounge, space at Puyallup campus. While some decisions about the relocations are still in process, we have determined the following:

Moving Update - May 22, 2007
Group Existing Location New Location
Zone 1 Move (June 15th-ish)
College Relations 4th floor Cascade Puyallup
Student Media Center 4th floor Cascade 4th floor Cascade (rm 400H)
Library Circulation Desk 4th floor Cascade 4th floor Cascade (stay in Library)
Pioneer Newspaper 4th floor Cascade C322
Staff Lounge 4th floor Cascade C240
Mail Room 3rd floor Cascade 2nd floor Cascade
Mac Lab 4th floor Cascade Sunrise N112
 
Zone 2 (July 15-Aug 15th-ish)
Financial Aid 3rd floor Cascade Partial Puyallup/Partial C326
Access & Disability 3rd floor Cascade Sunrise ( N115)
Work Force/Job Connection 3rd floor Cascade Sunrise (N118)
Testing 3rd floor Cascade Sunrise (N117)
Cashier 3rd floor Cascade Performance Lounge (C421)
Registrar 3rd floor Cascade Performance Lounge (C421)
Registration 3rd floor Cascade Performance Lounge (C421)
Admissions 3rd floor Cascade Performance Lounge (C421)
Advising 3rd floor Cascade Sunrise (N117/118)
Women & Family Services 3rd floor Cascade Sunrise (N115)
VSO/Eval 3rd floor Cascade Performance Lounge (C421)
SMS 3rd floor Cascade Performance Lounge (C421)
Security 3rd floor Cascade Performance Lounge (C421)

The PC lab in N112 will be merging with the lab currently in N113 after the end of summer quarter.

The following classrooms will be taken off-line during the renovation: